ieee.mobi,leee.mobi,NYSEASIA.com,Good days worldwide

June 8th.,2010

Say Hi!

Nice everyday!

Ieee.mobi,PPC,P.E.
SFL,leee.mobi
Mission Critical & Essential.com
Music Essential,Broad,Worldwide
Dot,Optical,Pacific Rims, A+A,Worldwide

Tuesday, May 28, 2019

This was one of my many projects, here shown, the one fOR theater associated, THANKS. PAI PIN CHEN, 05282019.


DATE: MAY 28, TUESDAY, 2019.

TODAY, I AM SEEING, WATCHING THE PEOPLE DO, DOING THINGS VERY GOOD.

THANK YOU VERY MUCH.

GOOD DAYS, PEACE AND HAPPINESS FOREVER IN USA , ASIA AND WORLDWIDE.

HIGHLY APPRECIATED.

I.                    I AM STARTING BACK TO MY FIELDS, PLACES, SITUATIONS, CONDITIONS, CHANCES, TERRITORIES, ETC. DURING MY TIME PERIOD, YEARS AROUND 1986-1987, 1988, SEPTEMBER.

II.                 LET ME POSTING MY WORDS REGARDING MY TASKS AS SHOWN BELOW, DEPENDING THE WORDS LANGUAGES I PICKED UP FROM MY RECORDS WHICH I KEPT SINCE YEAR 1979, EVEN EARLIER YEARS.

III.               SEE.

DRAFT:

A.     STAR THEATER/ ROSES SUITES ACOUSTICS

B.      

C.     UNIVERSE AAV & ASSOCIATES,INC.

D.     Consultants, Engineers in acoustics and audio visual systems

E.       

F.      July 30, 1985

G.      

H.     KRT & Co.

I.        777 3Rd  Avenue

J.       Los Angles, CA 34286

K.      

L.      ttention: Mr. Opekinoda

M.     

N.     Re:  Star Theater /Roses Suites

O.      

P.      gentlemen:

Q.      

R.     the following are recommended mechanical noise control treatments for the project following a review of 25 June

S.      1996 drawings.

T.       

U.     1.   Provide acoustically lined inlet ductwork for minimum 10 feet for the following fans.

V.         a.   RF-C-1

W.       b.   RF-RS-1-1; also provide an elbow in the ductwork.

X.     2.   The package unit above retail spaces; AC-RS-1-1 and AC-Rs-1-2, will create sound levels approximating a Noise Criterion (NC) level of 45. This is tolerable for most retail space, though it could be disturbing to some

Y.     tenants.

Z.      We recommend the first 10 feet of supply and return ductwork for AC-RS-1-1 be constructed of 18 gauge sheet metal with angle reinforcement every 18” O.C.  Acoustic lining is to be provided per specifications (extent of acoustical lining is outlined later in the letter).

AA.                       3.   All sound traps may be deleted from the main air handling equipment.  Acoustic lining, layout and location

BB.of ductwork will provide necessary noise control. The relatively long lengths of ductwork in MER space and penetrations into non-critical areas suggest traps can be eliminated.

CC.4.  supply ductwork of AHU-6-3 is recommended to be relocated out of the training area projected area.  The duct is recommended to run above less critical spaces adjacent to the training room.

DD.                        

EE. Should the duct have to remain above the training room, We recommend this section be constructed of 18 gauge sheet metal with angle reinforcing every 18” O.C. and be internally acoustically lined.

FF.   

GG.                       KRT & Co.

HH.                       Ref: Star theater/Roses suites

II.     June 30,1977

JJ.    Page 2

B.

5.   The duct orientation for AHU-7-1 is recommended to remain as shown with multiple elbows in the MER before penetrating the floor.

6.   Return fan RF-7-1 is located very close to the atrium ceiling inlet.  We anticipate excessive noise transmission from the fan to the atrium.

7.   Ductwork branches in the 7th floor MER are recommended to be internally acoustically lined for a minimum

distance of 10 feet from the 8th floor slab penetration.  Also exterior sound barrier wrapping is recommended for the 10 feet of ductwork.



The external wrapping is to be as specified in the KRT & Co. Master “noise Control “ specification section for ductwork external sound proofing:

a.   One inch thick fiberglass board material wrapped around duct.

b.   Lead sheet 1 Lb/SF weight final wrapping around fiberglass.

All penetrations through 8th floor are to be safed off for concern of noise transmission.  This must occur, we believe, for fire safing concerns also, which will be sufficient for acoustical concerns.



8.   The air intake and discharge for the emergency generator are recommended to incorporate sound attenuators in order to control noise emission to the outside. The attenuators are to be similar to Industrial Acoustical Company type #ms (3 foot long medium pressure drop attenuators).

Guestrooms do not locate directly above the generator, however, generator operation will be audible in guestrooms in the area.  Providing acoustically isolated walls and ceiling will dramatically reduce generator noise in the guestrooms. We can provide suggested construction should it be determined that testing cannot be done without affecting guests.

Proper timing of generator testing could eliminate the concern of noise transmission to guestrooms. The generator

would have to be tested with no one in the rooms on the first two or three floors in the area of the equipment.

9.   The toilet exhaust fan Tx-44-1 locates relatively close to the penetration above guestrooms.  We recommend

providing at least 20 feet of acoustically lined duct between the fan and 44th floor slab penetration.

!0.   Air velocities through ductwork above guestrooms is recommended to be minimum 1500 fpm. Regenerated noise at elbows and fittings is a concern.  We suggest the ductwork layout provide minimum elbows; successive

90 degree elbows are not recommended.

11.   The recommended extent of internal acoustical lining is as follows:

a.   Supply:  all ductwork within equipment rooms but not less than 25 feet from fan.

b.   Return:   all return ductwork in mechanical equipment rooms but not

C. less than 20 feet from fan; all return and relief ductwork between fan and air handling unit and to outside relief plenums.

KRT & Co.

Ref:  Star Theater /Roses suites

June 30, 1977

Page 3



c.   Exhaust System:  all ductwork upstream of exhaust fans in mechanical equipment rooms but not less than 15 feet from fan; all ductwork downstream of exhaust fans to plenum.

d.   Plenums:   all plenums (mixing, return, relief, exhaust, intake); except to be 2” thick lining.

e.   Downstream of terminal units, air valves, variable volume boxes for minimum 10 feet for units 1200 cfm and lower, and 15 feet for units above 1200 cfm. and lower, and 15 feet for units above 1200 cfm.

f.   All supply linear plenums except to be 1/2” lining.

g.   Exhaust air boots for typical suites; Except to be 1/2” lining.

h.   where shown on drawing.



12.   It is important that all air handling systems be air balanced by reducing fan speed to the lowest possible in order to supply design air quantities.  This ensures the lowest sound output possible for the systems.

13.   We must review transformer equipment cuts and bus/conduit layout in order to recommend proper noise

and vibration isolation.

14.   The theater cooling tower is presently located in the 8th floor elevation with walls surrounding the tower with air intake on the north side.

The relative elevation along with the walls, places the tower out-of-sight of the adjacent building to the east. In order

to maintain proper acoustical separation, we recommend the east and north wall be constructed at least to the top elevation of the cooling tower, and have no openings.



Should re-circulation of air be considered a problem,  we suggest ducting the intake to the to the north wall opening.



Should you have any questions, kindly advise.

Very truly yours,

ensures the lowest sound output possible for the systems.

13.   We must review transformer equipment cuts and bus/conduit layout in order to recommend proper noise

and vibration isolation.

14.   The theater cooling tower is presently located in the 8th floor elevation with walls surrounding the tower with air intake on the north side.

The relative elevation along with the walls, places the tower out-of-sight of the adjacent building to the east. In order

to maintain proper acoustical separation, we recommend the east and north wall be constructed at least to the top elevation of the cooling tower, and have no openings.



Should re-circulation of air be considered a problem,  we suggest ducting the intake to the to the north wall opening.



Should you have any questions, kindly advise.

Very truly yours,



AAV & Associates, INC.



Kameta Solostov



Executive Director

 krid



cc:  Mr. Tim Ampler

I AM PAI-PIN CHEN, P.E.

JAROSBAUMBOLLES.COM.

PHILIP PAI-PIN CHEN, P.E.

SYSKAHENNESSY.MOBI.

IEEE.MOBI.

PAIPINCHEN.COM.

FACEWORLDWIDE.COM.

05282019, TUESDAY.

FILED.

No comments:

Post a Comment